KINO’OLE STREET RESURFACING BEGINS MONDAY, FEB. 13

0
gie5Gpn4T

KINO’OLE STREET RESURFACING BEGINS MONDAY, FEB. 13

 

Department of Public Works Highways-Maintenance Division will be resurfacing Kino’ole Street from Wailuku Drive to Mohouli Street. All roadwork will take place 8 a.m. to 5 p.m. Monday through Friday, weather permitting,

 

DPW is requesting the public’s assistance that no cars be parked on the roadside for the duration of the resurfacing work. Expect one lane closure during the day, with Hawai’i Police Department directing traffic. Below is the anticipated work/section schedule, and is subject to change.

 

Section Location Timeline of work
1 Wailuku Dr. to Waiānuenue Ave. February 13-14, 2023
2 Waiānuenue Ave. to Haili St. February 15-16
3 Haili St. to Mamo St. February 17 and 21
4 Mamo St. to Ponohawai St. February 22-23
5 Ponohawai St. to Hualalai St. February 24 and 27
6 Hualalai St. to Wailoa St. February 28-March 1
7 Wailoa St. to Mohouli St. March 2-3